=====EBeam1 is UP=====
EBeam1 is back UP


=====Christmas Lab Shutdown: Dec 22-25=====
Late this morning, the hoist motor was finally delivered, and as soon as it arrived I started the installation.
Users,
I then tested the Egun operation due to the new high voltage feed throughs that were installed earlier this week.
To perform annual maintenance, we are planning to have the lab shut down from '''''9 am on Monday December 22 through 9 am Friday December 26th'''''.


Please plan accordingly.
All tests were completed without issue. System UP.
- Peder Lenvik
// 04:23, 25 July 2025 (UTC)
// [[User:John_d|Demis D. John]] 02:03, 27 November 2025 (UTC)


=====Announcements moved=====
===== SignupMonkey + Wiki: Off-Campus Access=====
Please check the announcements in SignupMonkey for equipment notifications.
Due to a DDoS attack affecting the Signupmonkey server, we have restricted access to the website to US locations only, including both the Nanofab Wiki and Signupmonkey.
// [[User:John_d|Demis D. John]] 02:03, 27 November 2025 (UTC)

If you are off-campus and experiencing issues, please utilize the UCSB VPN to access our sites. Here are the installation instructions for VPN on your device. You will need your UCSB NetID for download and installation - you would have received a UCSB NetID when you started using the NanoFab:

https://it.ucsb.edu/ivanti-secure-access-campus-vpn/get-connected-campus-vpn

-- Vraj
// [[User:John_d|Demis D. John]] 20:08, 22 April 2025 (UTC)

=====Suss SB6-8E=====
We found a blown resistor (and a questionable op amp) on one of the boards that contains the z-axis motor circuit. However, we still cannot get the tool to initialize. Next we will try swapping out the hard drive again and run some more tests.

I will send out an update once we have one.
-Aidan
// [[User:John_d|Demis D. John]] 00:35, 8 December 2024 (UTC)

=====ICP1 Down=====
The board we were waiting on arrived, but it did not resolve the tool issue. We are working with Panasonic on the next steps.
//[[User:Mehalana v|Vraj Mehalana]] 14:17, 1 March 2024 (PST)


<!--
<!--

Latest revision as of 06:39, 3 December 2025

Christmas Lab Shutdown: Dec 22-25

Users, To perform annual maintenance, we are planning to have the lab shut down from 9 am on Monday December 22 through 9 am Friday December 26th.

Please plan accordingly. - Peder Lenvik // Demis D. John 02:03, 27 November 2025 (UTC)

Announcements moved

Please check the announcements in SignupMonkey for equipment notifications. // Demis D. John 02:03, 27 November 2025 (UTC)