===== SEM#1(FEI) ===== |
|||
The vendor will be here on Wednesday to address the charging issue at higher mags. |
|||
[[User:Silva|Silva]] 16:40, 25 February 2019 (PST) |
|||
<!---------- end of Equipment Status ------------> |
<!---------- end of Equipment Status ------------> |
Revision as of 00:40, 26 February 2019
Equipment Status
Suss Bonder
Suss fieldservice found several issues with the system. Suss will evaluate the issues and recommend possible solutions. // Silva 21:36, 13 February 2019 (PST)
E-Beam#1
The system is down. The E-Beam#1 power supply and control upgrade started today. We hope to complete the process within 10 business days. We will keep you posted as progress is made. // Silva 21:45, 11 February 2019 (PST)
ASML DUV: PM March 12 to 15th
ASML will be performing their periodic maintenance on the DUV stepper from Tuesday March 12th through Friday March 15th. Please schedule your work accordingly. // John d 11:02, 15 February 2019 (PST)
SEM#1(FEI)
The vendor will be here on Wednesday to address the charging issue at higher mags. Silva 16:40, 25 February 2019 (PST)