=====FEI SEM#1 Replacement Project=====
=====Lab is Open=====
The FEI SEM #1 will be removed and replaced starting Friday March 17th. Both SEMs will be shut down and the SEM room will be off limits beginning at 8 am Friday and return to normal operations Tuesday morning the 21st.

//[[User:Mehalana v|Vraj Mehalana]] 10:55, 16 March 2023 (PDT)
All suits have been pulled and clean sheets have been put up. All personal items left behind can be found in the boxes in the lobby.
<!--feedBurner name="UCSBNanofab-Announcements" /-->

<!-- Description of the RSS feed -->
Please sign up for your hanger spot.

THE LAB IS NOW OPEN FOR BUSINESS

Thank you for your patience during shutdown activities.
-- [[Peder Lenvik]]

// [[User:John_d|Demis D. John]] 03:34, 3 January 2025 (UTC)

=====New Gowns in Jan=====
We are required to switch to new gowns in January. The new gowns won’t have pockets, but you are allowed to purchase cleanroom tool belts. Please ask staff for tool belts you can use.
// [[User:John_d|Demis D. John]] 03:34, 3 January 2025 (UTC)

=====KLA P7 Profilometer: Down=====
The KLA remains down awaiting parts. This part order has been expedited to the extent possible and should be here in the next few days.

Thanks
Bill Millerski
// [[User:John_d|Demis D. John]] 03:30, 3 January 2025 (UTC)

=====Oxford ALD+Ion Mill=====
Unfortunately, we are still experiencing issues with the tool and it remains unavailable. This tool issue remains my highest priority, and we are working closely with the vendor to try and resolve this issue as soon as possible. -- Bill Millerski
// [[User:John_d|Demis D. John]] 03:29, 3 January 2025 (UTC)

=====Holography/PL: HeCd Laser Down Mon Dec 16th=====
The 325nm UV Laser will be unavailable from Mon. Dec 16th, through the christmas shutdown, and will be available again soon after Monday Jan 6th.
We will be installing the refurbished laser which will have higher output power.

Holography will be unavailable during this time, but all other PL lasers will be available.
// [[User:John_d|Demis D. John]] 03:28, 3 January 2025 (UTC)

=====Suss SB6-8E=====
We found a blown resistor (and a questionable op amp) on one of the boards that contains the z-axis motor circuit. However, we still cannot get the tool to initialize. Next we will try swapping out the hard drive again and run some more tests.

I will send out an update once we have one.
-Aidan
// [[User:John_d|Demis D. John]] 00:35, 8 December 2024 (UTC)

=====ICP1 Down=====
The board we were waiting on arrived, but it did not resolve the tool issue. We are working with Panasonic on the next steps.
//[[User:Mehalana v|Vraj Mehalana]] 14:17, 1 March 2024 (PST)

<!--
<!--
SEE THE BOTTOM OF THIS PAGE FOR DETAILED INSTRUCTIONS ON ADDING NEWS ITEMS.
SEE THE BOTTOM OF THIS PAGE FOR DETAILED INSTRUCTIONS ON ADDING NEWS ITEMS.
Line 11: Line 53:
>> Use two slashes // and FOUR tilde's to insert your signature at the end of your post: //~~~~
>> Use two slashes // and FOUR tilde's to insert your signature at the end of your post: //~~~~
-->
-->

<!---------------------------------------------->
<!------------- Equipment Status ---------------->
===== Unaxis Etch: Down =====
We had to take the VAT controller off of this module to get the ICP-PECVD running. I have no immediate ETA for this system coming back online. Until we get this system running again you will need to use the Oxford Cobra system. -- Tony
// [[User:John d|John d]] 09:35, 13 February 2023 (PST)

===== Dektak XT ready for training =====
We have replaced the Dektak 6M with a new Dektak XT profilometer. The system is available for training, please [[Aidan_Hopkins|contact the tool supervisor]].
// [[User:John d|John d]] 10:08, 7 February 2023 (PST)

===== Au Plating: UP=====
only the full 100mm wafer fixture is available at the moment. You can plate smaller pieces on it with no issues.
// [[User:Mehalana v|Vraj Mehalana]] 12:35, 15 March 2023 (PDT)

<!---------- end of Equipment Status ------------>
<!---------DO NOT EDIT BELOW THIS LINE----------->
<!---------DO NOT EDIT BELOW THIS LINE----------->
<endfeed />
<endfeed />
Line 32: Line 58:
<!--------------------------------------------
<!--------------------------------------------
====== HOW TO ADD ITEMS ======
====== HOW TO ADD ITEMS ======

* You can copy/paste the example below for a new news item.
* You can copy/paste the example below for a new news item.
* Use level 5 heading for each item (5 equal signs surrounding the title) - they will show up as separate RSS items this way. (This looks best on the Wiki homepage)
* Use level 5 heading for each item (5 equal signs surrounding the title) - they will show up as separate RSS items this way. (This looks best on the Wiki homepage)

Latest revision as of 03:39, 3 January 2025

Lab is Open

All suits have been pulled and clean sheets have been put up. All personal items left behind can be found in the boxes in the lobby.

Please sign up for your hanger spot.

THE LAB IS NOW OPEN FOR BUSINESS

Thank you for your patience during shutdown activities. -- Peder Lenvik

// Demis D. John 03:34, 3 January 2025 (UTC)

New Gowns in Jan

We are required to switch to new gowns in January. The new gowns won’t have pockets, but you are allowed to purchase cleanroom tool belts. Please ask staff for tool belts you can use. // Demis D. John 03:34, 3 January 2025 (UTC)

KLA P7 Profilometer: Down

The KLA remains down awaiting parts. This part order has been expedited to the extent possible and should be here in the next few days.

Thanks Bill Millerski // Demis D. John 03:30, 3 January 2025 (UTC)

Oxford ALD+Ion Mill

Unfortunately, we are still experiencing issues with the tool and it remains unavailable. This tool issue remains my highest priority, and we are working closely with the vendor to try and resolve this issue as soon as possible. -- Bill Millerski // Demis D. John 03:29, 3 January 2025 (UTC)

Holography/PL: HeCd Laser Down Mon Dec 16th

The 325nm UV Laser will be unavailable from Mon. Dec 16th, through the christmas shutdown, and will be available again soon after Monday Jan 6th. We will be installing the refurbished laser which will have higher output power.

Holography will be unavailable during this time, but all other PL lasers will be available. // Demis D. John 03:28, 3 January 2025 (UTC)

Suss SB6-8E

We found a blown resistor (and a questionable op amp) on one of the boards that contains the z-axis motor circuit. However, we still cannot get the tool to initialize. Next we will try swapping out the hard drive again and run some more tests.

I will send out an update once we have one. -Aidan // Demis D. John 00:35, 8 December 2024 (UTC)

ICP1 Down

The board we were waiting on arrived, but it did not resolve the tool issue. We are working with Panasonic on the next steps. //Vraj Mehalana 14:17, 1 March 2024 (PST)