Tube Furnace Wafer Bonding (Thermco): Difference between revisions
Jump to navigation
Jump to search
No edit summary |
Millerski w (talk | contribs) (Updated SOP) |
||
Line 12: | Line 12: | ||
|toolid=43 |
|toolid=43 |
||
}} |
}} |
||
= |
=About= |
||
This wafer fusion furnace is a custom built unit designed for the fusion of different material types (such InP and Si) to create new heterostructures for novel electronic and optoelectronic devices. Custom made bonding fixtures are loaded into the furnace through a purged glove-box that is oxygen free to below 10 ppm with a dew point near -80°C. The furnace is nitrogen purged and can operate up from 200°C to 1200°C. Many different materials are allowed and maximum temperature is dependent on the materials themselves, to avoid contamination of the furnace. |
This wafer fusion furnace is a custom built unit designed for the fusion of different material types (such InP and Si) to create new heterostructures for novel electronic and optoelectronic devices. Custom made bonding fixtures are loaded into the furnace through a purged glove-box that is oxygen free to below 10 ppm with a dew point near -80°C. The furnace is nitrogen purged and can operate up from 200°C to 1200°C. Many different materials are allowed and maximum temperature is dependent on the materials themselves, to avoid contamination of the furnace. |
||
= |
=Detailed Specifications= |
||
*Temperatures 200°C to 1200°C |
*Temperatures 200°C to 1200°C |
||
*4 inch diameter furnace |
*4 inch diameter furnace |
||
Line 22: | Line 23: | ||
*Dew point near -80°C |
*Dew point near -80°C |
||
*Custom bonding fixtures of various materials allowed |
*Custom bonding fixtures of various materials allowed |
||
= Operation Procedures = |
|||
* [https://wiki.nanofab.ucsb.edu/w/images/2/2f/Tube_Furnace_Wafer_Bonding_SOP.pdf Tube Furnace Operation Procedure] |
Latest revision as of 21:55, 30 October 2023
|
About
This wafer fusion furnace is a custom built unit designed for the fusion of different material types (such InP and Si) to create new heterostructures for novel electronic and optoelectronic devices. Custom made bonding fixtures are loaded into the furnace through a purged glove-box that is oxygen free to below 10 ppm with a dew point near -80°C. The furnace is nitrogen purged and can operate up from 200°C to 1200°C. Many different materials are allowed and maximum temperature is dependent on the materials themselves, to avoid contamination of the furnace.
Detailed Specifications
- Temperatures 200°C to 1200°C
- 4 inch diameter furnace
- Nitrogen ambient at atmospheric pressure
- Oxygen control in glove box to less than 10 ppm
- Dew point near -80°C
- Custom bonding fixtures of various materials allowed