Template:Announcements: Difference between revisions
(Suss bonder update) |
(ebl up) |
||
Line 1: | Line 1: | ||
<startfeed /> |
<startfeed /> |
||
=====JEOL JBX-6300FS===== |
=====JEOL JBX-6300FS: Up===== |
||
System is up and running reliably.// [[User:John_d|Demis D. John]] 09:07, 15 August 2024 (PDT) |
|||
JEOL have applied a temporary fix that after overnite testing has shown to be robust. A full fix will require new boards to arrive from Japan in about a week. |
|||
So feel confident about using the tool in the interim. If any issues, let me know immediately.// [[User:John_d|Demis D. John]] 15:52, 6 August 2024 (PDT) |
|||
=====Wafer Bonder, (Suss SB6-8E)===== |
=====Wafer Bonder, (Suss SB6-8E)===== |
Revision as of 16:07, 15 August 2024
JEOL JBX-6300FS: Up
System is up and running reliably.// Demis D. John 09:07, 15 August 2024 (PDT)
Wafer Bonder, (Suss SB6-8E)
A third party bonder repair company will be out here the week of the 26th. The goal is to install the new top heater and then to do a full PM. If all goes well the tool will be available to use late that week. I’ll send out another email once I have more information. Thanks, Aidan.
// Demis D. John 15:52, 6 August 2024 (PDT)
Unaxis ICP-PECVD Update
Unfortunately the shipment of repaired parts was significantly delayed. I will be installing them and testing on Tuesday. With any luck the system will be available Tuesday evening.
Tony
//Vraj Mehalana 16:26, 26 July 2024 (PDT)
ICP1 Down
The board we were waiting on arrived, but it did not resolve the tool issue. We are working with Panasonic on the next steps. //Vraj Mehalana 14:17, 1 March 2024 (PST)
Lab Access Changes: Symmetry App
The iris scanner has been decommissioned. Please use the card reader which supports:
-Physical card
-Mobile phone via Symmetry App
//Vraj Mehalana 16:59, 14 June 2024 (PDT)