Template:Announcements

From UCSB Nanofab Wiki
Revision as of 23:36, 16 July 2023 by Mehalana v (talk | contribs)
Jump to navigation Jump to search

SEM 1 Update

The field service engineer has finished with alignments and the SEM is up and running. The FSE will be back late Monday morning to do some fine adjustments. Please let us know if you encounter any issues. //Vraj Mehalana 16:36, 16 July 2023 (PDT)

SEM 2 Update

Once SEM 1 is up we’ll wait for at least a week before we decommission SEM 2. //Vraj Mehalana 11:16, 12 July 2023 (PDT)

Plasma Activation (EVG 810)

We have received almost all the replacement parts for the tool except the new chuck. The original delivery date of mid June has now been pushed out to early September and they have stated that this is the best that their supplier can do. I will not be installing any new parts on the tool until we have everything. Runs will still require Staff supervision until then. //Vraj Mehalana 18:01, 2 May 2023 (PDT)