EBeam1 is UP
EBeam1 is back UP
Late this morning, the hoist motor was finally delivered, and as soon as it arrived I started the installation.
I then tested the Egun operation due to the new high voltage feed throughs that were installed earlier this week.
All tests were completed without issue. System UP.
// 04:23, 25 July 2025 (UTC)
SignupMonkey + Wiki: Off-Campus Access
Due to a DDoS attack affecting the Signupmonkey server, we have restricted access to the website to US locations only, including both the Nanofab Wiki and Signupmonkey.
If you are off-campus and experiencing issues, please utilize the UCSB VPN to access our sites. Here are the installation instructions for VPN on your device. You will need your UCSB NetID for download and installation - you would have received a UCSB NetID when you started using the NanoFab:
https://it.ucsb.edu/ivanti-secure-access-campus-vpn/get-connected-campus-vpn
-- Vraj
// Demis D. John 20:08, 22 April 2025 (UTC)
Suss SB6-8E
We found a blown resistor (and a questionable op amp) on one of the boards that contains the z-axis motor circuit. However, we still cannot get the tool to initialize. Next we will try swapping out the hard drive again and run some more tests.
I will send out an update once we have one.
-Aidan
// Demis D. John 00:35, 8 December 2024 (UTC)
ICP1 Down
The board we were waiting on arrived, but it did not resolve the tool issue. We are working with Panasonic on the next steps.
//Vraj Mehalana 14:17, 1 March 2024 (PST)