Olympus DSX Microscope: Down
After speaking with Olympus it looks like there is a problem with the polarizer that is interfering with basic system initialization. I'm waiting for the repair quote and will update everyone when we know more.
-- Tony Bosch
// Demis D. John 20:41, 5 February 2025 (UTC)
ASML Quarterly Maintenance: Mon Feb 10th
We will be performing the Quarterly PM on the ASML next week, Mon Feb 10th, through at least Thurs Feb 13th, possibly into Friday.
// Demis D. John 19:44, 4 February 2025 (UTC)
ICP #2 Maint: Complete
The maintenance is completed and the tool is finishing up an O2 clean run. We are still seeing a 0.04-0.05 Pa actual pressure difference in the software (as before the maint work) which we will address tomorrow, as the tool needs time to reach base pressure. -- Lee Sawyer
//Demis D. John 02:01, 5 February 2025 (UTC)
Oxford ALD+Ion Mill: UP
The tool is useable and in its original condition. If you had a reservation under the previous tool designation it has already been moved over for you.
Chamber 1 is operational and available for use. However, only recipes that run at 300C are to be ran on the tool, as the current thermocouple is only calibrated for that temperature at this time.
Please use the original tool name on SUM to make all future tool reservations.
There is no longer a need for supplemental training. If you have been previously trained on the tool but not received the supplemental training, you can once again reserve and use the tool.
Please feel free to email me directly with any questions you may have.
Thanks
Bill Millerski
UCSB
//Demis D. John 19:48, 4 February 2025 (UTC)
New Gowns: Toolbelts purchases
We are required to switch to new gowns in January. The new gowns won’t have pockets, but you are allowed to purchase cleanroom tool belts. Please ask staff for which tool belts you can purchase.
Two vendors for cleanroom belts we are using are listed here, you may request others:
// Demis D. John 03:34, 3 January 2025 (UTC)
Suss SB6-8E
We found a blown resistor (and a questionable op amp) on one of the boards that contains the z-axis motor circuit. However, we still cannot get the tool to initialize. Next we will try swapping out the hard drive again and run some more tests.
I will send out an update once we have one.
-Aidan
// Demis D. John 00:35, 8 December 2024 (UTC)
ICP1 Down
The board we were waiting on arrived, but it did not resolve the tool issue. We are working with Panasonic on the next steps.
//Vraj Mehalana 14:17, 1 March 2024 (PST)