=====Wafer Coater (S Cubed Flexi) - S3 field service=====
=====Christmas Lab Shutdown: Dec 22-25=====
S3 will be on-site looking into our hand 2 issues on Wednesday May 3rd and 4th. They will be confirming Monday so there is a chance those days get shifted. Please plan your processing accordingly as the system will not be available while they are here looking into the problem.
Users,
//[[User:Mehalana v|Vraj Mehalana]] 13:54, 28 April 2023 (PDT)
To perform annual maintenance, we are planning to have the lab shut down from '''''9 am on Monday December 22 through 9 am Friday December 26th'''''.
=====FEI SEM#1 Replacement Project=====

The FEI SEM #1 will be removed and replaced starting Friday March 17th. Both SEMs will be shut down and the SEM room will be off limits beginning at 8 am Friday and return to normal operations Tuesday morning the 21st.
Please plan accordingly.
//[[User:Mehalana v|Vraj Mehalana]] 10:55, 16 March 2023 (PDT)
- Peder Lenvik
<!--feedBurner name="UCSBNanofab-Announcements" /-->
// [[User:John_d|Demis D. John]] 02:03, 27 November 2025 (UTC)
<!-- Description of the RSS feed -->

=====Announcements moved=====
Please check the announcements in SignupMonkey for equipment notifications.
// [[User:John_d|Demis D. John]] 02:03, 27 November 2025 (UTC)

<!--
<!--
SEE THE BOTTOM OF THIS PAGE FOR DETAILED INSTRUCTIONS ON ADDING NEWS ITEMS.
SEE THE BOTTOM OF THIS PAGE FOR DETAILED INSTRUCTIONS ON ADDING NEWS ITEMS.
Line 14: Line 19:
>> Use two slashes // and FOUR tilde's to insert your signature at the end of your post: //~~~~
>> Use two slashes // and FOUR tilde's to insert your signature at the end of your post: //~~~~
-->
-->
<!---------------------------------------------->
<!------------- Equipment Status ---------------->
===== Unaxis Etch: Down =====
We had to take the VAT controller off of this module to get the ICP-PECVD running. I have no immediate ETA for this system coming back online. Until we get this system running again you will need to use the Oxford Cobra system. -- Tony
// [[User:John d|John d]] 09:35, 13 February 2023 (PST)
===== Au Plating: UP=====
only the full 100mm wafer fixture is available at the moment. You can plate smaller pieces on it with no issues.
// [[User:Mehalana v|Vraj Mehalana]] 12:35, 15 March 2023 (PDT)
<!---------- end of Equipment Status ------------>
<!---------DO NOT EDIT BELOW THIS LINE----------->
<!---------DO NOT EDIT BELOW THIS LINE----------->
<endfeed />
<endfeed />

Latest revision as of 06:39, 3 December 2025

Christmas Lab Shutdown: Dec 22-25

Users, To perform annual maintenance, we are planning to have the lab shut down from 9 am on Monday December 22 through 9 am Friday December 26th.

Please plan accordingly. - Peder Lenvik // Demis D. John 02:03, 27 November 2025 (UTC)

Announcements moved

Please check the announcements in SignupMonkey for equipment notifications. // Demis D. John 02:03, 27 November 2025 (UTC)