Template:Announcements: Difference between revisions

From UCSB Nanofab Wiki
Jump to navigation Jump to search
Content deleted Content added
Feed Appended
mNo edit summary
 
(329 intermediate revisions by 7 users not shown)
Line 1: Line 1:
<startfeed />
<startfeed />

=====E-Beam #4 (CHA) - EB4 is down=====
=====Christmas Lab Shutdown: Dec 22-25=====
We need to replace a part on the source shutter. We should have it on Monday. I'll update when the tool is available.
Users,
//[[User:Mehalana v|Vraj Mehalana]] 15:26, 28 April 2023 (PDT)
To perform annual maintenance, we are planning to have the lab shut down from '''''9 am on Monday December 22 through 9 am Friday December 26th'''''.
=====Wafer Coater (S Cubed Flexi) - S3 field service=====

S3 will be on-site looking into our hand 2 issues on Wednesday May 3rd and 4th. They will be confirming Monday so there is a chance those days get shifted. Please plan your processing accordingly as the system will not be available while they are here looking into the problem.
Please plan accordingly.
//[[User:Mehalana v|Vraj Mehalana]] 13:54, 28 April 2023 (PDT)
- Peder Lenvik
=====FEI SEM#1 Replacement Project=====
// [[User:John_d|Demis D. John]] 02:03, 27 November 2025 (UTC)
The FEI SEM #1 will be removed and replaced starting Friday March 17th. Both SEMs will be shut down and the SEM room will be off limits beginning at 8 am Friday and return to normal operations Tuesday morning the 21st.

//[[User:Mehalana v|Vraj Mehalana]] 10:55, 16 March 2023 (PDT)
<!--feedBurner name="UCSBNanofab-Announcements" /-->
=====Announcements moved=====
Please check the announcements in SignupMonkey for equipment notifications.
<!-- Description of the RSS feed -->
// [[User:John_d|Demis D. John]] 02:03, 27 November 2025 (UTC)

<!--
<!--
SEE THE BOTTOM OF THIS PAGE FOR DETAILED INSTRUCTIONS ON ADDING NEWS ITEMS.
SEE THE BOTTOM OF THIS PAGE FOR DETAILED INSTRUCTIONS ON ADDING NEWS ITEMS.
Line 17: Line 19:
>> Use two slashes // and FOUR tilde's to insert your signature at the end of your post: //~~~~
>> Use two slashes // and FOUR tilde's to insert your signature at the end of your post: //~~~~
-->
-->
<!---------------------------------------------->
<!------------- Equipment Status ---------------->
===== Unaxis Etch: Down =====
We had to take the VAT controller off of this module to get the ICP-PECVD running. I have no immediate ETA for this system coming back online. Until we get this system running again you will need to use the Oxford Cobra system. -- Tony
// [[User:John d|John d]] 09:35, 13 February 2023 (PST)
===== Au Plating: UP=====
only the full 100mm wafer fixture is available at the moment. You can plate smaller pieces on it with no issues.
// [[User:Mehalana v|Vraj Mehalana]] 12:35, 15 March 2023 (PDT)
<!---------- end of Equipment Status ------------>
<!---------DO NOT EDIT BELOW THIS LINE----------->
<!---------DO NOT EDIT BELOW THIS LINE----------->
<endfeed />
<endfeed />

Latest revision as of 06:39, 3 December 2025

Christmas Lab Shutdown: Dec 22-25

Users, To perform annual maintenance, we are planning to have the lab shut down from 9 am on Monday December 22 through 9 am Friday December 26th.

Please plan accordingly. - Peder Lenvik // Demis D. John 02:03, 27 November 2025 (UTC)

Announcements moved

Please check the announcements in SignupMonkey for equipment notifications. // Demis D. John 02:03, 27 November 2025 (UTC)