=====Stepper #1 (GCA 6300) - Scheduled Maintenance=====
The tool will be undergoing maintenance and be unavailable the following dates and times:


=====Suss SB6-8E=====
1-18-24 at 8:00am to 1-18-24 at 6:00pm
When the vendor came in to install the new top heater he wasn't able to get the z-axis (elevator motor) to move. He was able to install the new heater and do a PM on the rest of the tool. We are ordering a new z-axis controller on the recommendation of the vendor. If all goes well this should solve the issue and make the bonder fully operational. I'll send out an email once the new controller has been installed.


-Aidan
Please plan your processing activities accordingly.
//[[User:Mehalana v|Vraj Mehalana]] 12:43, 3 September 2024 (PDT)


=====ICP1 Down=====
Bill Millerski
The board we were waiting on arrived, but it did not resolve the tool issue. We are working with Panasonic on the next steps.
//[[User:Mehalana v|Vraj Mehalana]] 14:17, 1 March 2024 (PST)


=====Lab Access Changes: Symmetry App=====
//[[User:Mehalana v|Vraj Mehalana]] 21:49, 21 December 2023 (PST)
The iris scanner has been decommissioned. Please use the card reader which supports:


-Physical card
===== Stepper #2 (GCA Autostep 200) - Scheduled Maintenance=====
The tool will be undergoing maintenance and be unavailable the following dates and times:

1-15-24 at 8:00am to 1-17-24 at 6:00pm

Please plan your processing activities accordingly.

//[[User:Mehalana v|Vraj Mehalana]] 21:49, 21 December 2023 (PST)

=====DUV is down - Update=====
Parts were scheduled to arrive last Thursday but were delayed due to the weather that day. Tracking status never updated from pending after that point so I had to wait 7 days before filing a claim with FEDEX. Hopefully the claim and associated dollar value will get them to start looking for the package, and we are also exploring other options.

I'll hopefully send out another update late next week with some idea of when we will have parts.
//[[User:Mehalana v|Vraj Mehalana]] 15:27, 2 January 2024 (PST)

=====PECVD2 Planned Down Time for Maintenance 12-11-23=====
PECVD2 will be going down on Monday 12-11-23 at 10:00am for replacement of the RF connector and RF Electrode.

When the work is complete, the process group will be running tests for the remainder of the afternoon.

//[[User:Mehalana v|Vraj Mehalana]] 14:07, 13 December 2023 (PST)
=====Year End Shutdown=====
We will be shutting down lab operations Tuesday Dec 26th at 9 am for year end maintenance activities. The current plan is to be back open for operations Thursday Dec 28th at 2 pm.
The staff will be on Holiday Dec 25th & 26th, and January 1st & 2nd.

//[[User:Mehalana v|Vraj Mehalana]] 14:39, 16 November 2023 (PST)

=====Job Opening: Process Engineer=====
The Nanofab has a current job opening for a Process/Wafer-Fab Engineer, see the [https://wiki.nanofab.ucsb.edu/wiki/Nanofab_Job_Postings NanoFab Job Openings page] for details.

//[[User:Mehalana v|Vraj Mehalana]] 14:52, 30 October 2023 (PDT)

=====Lab Access Changes: Symmetry App=====
Card/Iris scanner access is still currently enabled. However we will be moving to a smartphone-based access system. '''IMPORTANT''': check your email to setup the new smartphone access system, so you will be ready when we switch to the new system. Look for an email titled '''''"Invitation to Access Symmetry App"'''''.


-Mobile phone via Symmetry App
// [[User:John d|John d]] 13:49, 7 November 2023 (PST)


//[[User:Mehalana v|Vraj Mehalana]] 16:59, 14 June 2024 (PDT)
=====Wafer Bonder, (Suss SB6-8E)=====
SUSS now aims to be on site in early February. I’ll will send out an email once I get confirmation for a specific date.
//[[User:Mehalana v|Vraj Mehalana]] 14:23, 13 December 2023 (PST)


<!--
<!--

Latest revision as of 00:45, 7 November 2024

Suss SB6-8E

When the vendor came in to install the new top heater he wasn't able to get the z-axis (elevator motor) to move. He was able to install the new heater and do a PM on the rest of the tool. We are ordering a new z-axis controller on the recommendation of the vendor. If all goes well this should solve the issue and make the bonder fully operational. I'll send out an email once the new controller has been installed.

-Aidan //Vraj Mehalana 12:43, 3 September 2024 (PDT)

ICP1 Down

The board we were waiting on arrived, but it did not resolve the tool issue. We are working with Panasonic on the next steps. //Vraj Mehalana 14:17, 1 March 2024 (PST)

Lab Access Changes: Symmetry App

The iris scanner has been decommissioned. Please use the card reader which supports:

-Physical card

-Mobile phone via Symmetry App

//Vraj Mehalana 16:59, 14 June 2024 (PDT)