=====PECVD #2 update=====
===== SEM#1 update=====
The service engineer had to order some more parts for the SEM. He’ll be back tomorrow to continue troubleshooting the skewing issue. In the meantime, the tool is useable and is only showing the skewing issue within the mags of 5.5k to 8.5k. Please let me know if you encounter any other issues. Thanks, Aidan
We are continuing to work our way through the issue plaguing this system. Unfortunately running at lower power did not work. We will send updates more regularly to keep you all informed.
// [[User:John_d|Demis D. John]] 21:49, 28 May 2025 (UTC)


=====Dry Etch, Si Deep RIE (PlasmaTherm DSEIII) - IMPORTANT: Please Read!=====
Tony
We will be taking down the DSE to changeout the turbo pump next Wednesday (5/28). If all goes well the tool should only be down for the day. I’ll keep you updated with emails.
// [[User:Mehalana v|Vraj Mehalana]] 21:48, 21 May 2025 (UTC)


===== SignupMonkey + Wiki: Off-Campus Access=====
//[[User:Mehalana v|Vraj Mehalana]] 09:52, 7 February 2024 (PST)
Due to a DDoS attack affecting the Signupmonkey server, we have restricted access to the website to US locations only, including both the Nanofab Wiki and Signupmonkey.
=====MLA 150 Service Next Week - REMINDER=====
The MLA 150 will be down for a service visit from Tuesday February 6th to Thursday February 8th. The tool should be available in the evenings and it's possible the work will be completed by the end of Wednesday.


If you are off-campus and experiencing issues, please utilize the UCSB VPN to access our sites. Here are the installation instructions for VPN on your device. You will need your UCSB NetID for download and installation - you would have received a UCSB NetID when you started using the NanoFab:
Here's the schedule for when the tool will be unavailable:


https://it.ucsb.edu/ivanti-secure-access-campus-vpn/get-connected-campus-vpn
Tues (2/6): 11:30 am - 5 pm


-- Vraj
Wed (2/7): 8 am - 5 pm
// [[User:John_d|Demis D. John]] 20:08, 22 April 2025 (UTC)


=====New Gowns: Toolbelts purchases=====
Thurs (2/8) 8 am - 5 pm (if needed).
We are required to switch to new gowns in January. The new gowns won’t have pockets, but you are allowed to purchase cleanroom tool belts. Please ask staff for which tool belts you can purchase.


Two vendors for cleanroom belts we are using are listed here, you may request others:
-Lee
* [https://www.terrauniversal.com/tool-belt-pocket-49in-waist-white-altessa-grid-uniform-technology-4954-60a.html Uniform Technology Tool Belt] - note the waist size, the 49” belt fits up to ~36-38” waist.
* [https://www.fishersci.com/shop/products/cleanroom-fannypack-1-ea-white/NC0723118?searchHijack=true&searchTerm=cleanroom-fannypack-1-ea-white&searchType=Rapid&matchedCatNo=NC0723118 HiTEC Fannypack]


//[[User:Mehalana v|Vraj Mehalana]] 10:37, 1 February 2024 (PST)
// [[User:John_d|Demis D. John]] 03:34, 3 January 2025 (UTC)


===== MJB-3s Are up=====
=====Suss SB6-8E=====
We found a blown resistor (and a questionable op amp) on one of the boards that contains the z-axis motor circuit. However, we still cannot get the tool to initialize. Next we will try swapping out the hard drive again and run some more tests.
The servicing is completed for both of the MJB-3s. The stage issue with the IR system has been resolved as well.


I will send out an update once we have one.
//[[User:Mehalana v|Vraj Mehalana]] 15:51, 8 February 2024 (PST)
-Aidan
// [[User:John_d|Demis D. John]] 00:35, 8 December 2024 (UTC)


=====MA6 Service Next Week - REMINDER=====
=====ICP1 Down=====
The board we were waiting on arrived, but it did not resolve the tool issue. We are working with Panasonic on the next steps.
The MA-6 will be unavailable Tuesday Feb 6th from 8 am to roughly 5 pm for its annual service visit.
//[[User:Mehalana v|Vraj Mehalana]] 14:17, 1 March 2024 (PST)

The issue with the backside camera magnification getting stuck will be addressed during the visit.

-Lee

//[[User:Mehalana v|Vraj Mehalana]] 10:37, 1 February 2024 (PST)
=====RIE 5 is up=====
RIE 5 is up except for processes that use SiCl4.

//[[User:Mehalana v|Vraj Mehalana]] 09:39, 30 January 2024 (PST)
=====Dry Etch, Si Deep RIE (PlasmaTherm DSEIII) - DSE Update=====
We received most of the chamber assembly replacement parts today. We are still waiting on the lamps and chamber o-rings which are scheduled to be delivered in the next couple of days. Once we have all the parts, we'll start to reassemble the chamber.

I'll send out an update in the next 2-3 days.

Thanks,
//[[User:Mehalana v|Vraj Mehalana]] 10:58, 5 February 2024 (PST)

=====ICP #1 is down=====
The tool remains down. We did not find any "smoking gun" with the PC but did find that the PC's power supply had a non functional fan and the power supply did not test as good (granted it would still power up the PC). We will continue troubleshooting the PC issue in the morning.

-Lee

//[[User:Mehalana v|Vraj Mehalana]] 09:39, 30 January 2024 (PST)
=====EBeam3 Planned Maintenance 2/7/24 - 2/8/24=====
EBeam3 is scheduled to be down starting at 8:00am on 2/7/24 through 4:00pm on 2/8//24 so that we can install the new transfer arm.

Please plan accordingly.

//[[User:Mehalana v|Vraj Mehalana]] 09:28, 26 January 2024 (PST)
=====Oxford Cobra: Software bugs=====
The latest revision of software has several bugs: see email for details. We are working with Oxford to resolve via software upgrade.
// [[User:John_d|Demis D. John]] 10:08, 17 January 2024 (PST)

=====Job Opening: Process Engineer=====
The Nanofab has a current job opening for a Process/Wafer-Fab Engineer, see the [https://wiki.nanofab.ucsb.edu/wiki/Nanofab_Job_Postings NanoFab Job Openings page] for details.

//[[User:John d|Demis D. John]] 14:52, 30 October 2023 (PDT)

=====Lab Access Changes: Symmetry App=====
Card/Iris scanner access is still currently enabled. However we will be moving to a smartphone-based access system. '''IMPORTANT''': check your email to setup the new smartphone access system, so you will be ready when we switch to the new system. Look for an email titled '''''"Invitation to Access Symmetry App"'''''.

// [[User:John d|John d]] 13:49, 7 November 2023 (PST)

=====Wafer Bonder, (Suss SB6-8E)=====
SUSS aims to be on site in early February. We’ll will send out an email once I get confirmation for a specific date.
//[[User:Mehalana v|Vraj Mehalana]] 14:23, 13 December 2023 (PST)


<!--
<!--

Latest revision as of 22:24, 28 May 2025

SEM#1 update

The service engineer had to order some more parts for the SEM. He’ll be back tomorrow to continue troubleshooting the skewing issue. In the meantime, the tool is useable and is only showing the skewing issue within the mags of 5.5k to 8.5k. Please let me know if you encounter any other issues. Thanks, Aidan // Demis D. John 21:49, 28 May 2025 (UTC)

Dry Etch, Si Deep RIE (PlasmaTherm DSEIII) - IMPORTANT: Please Read!

We will be taking down the DSE to changeout the turbo pump next Wednesday (5/28). If all goes well the tool should only be down for the day. I’ll keep you updated with emails. // Vraj Mehalana 21:48, 21 May 2025 (UTC)

SignupMonkey + Wiki: Off-Campus Access

Due to a DDoS attack affecting the Signupmonkey server, we have restricted access to the website to US locations only, including both the Nanofab Wiki and Signupmonkey.

If you are off-campus and experiencing issues, please utilize the UCSB VPN to access our sites. Here are the installation instructions for VPN on your device. You will need your UCSB NetID for download and installation - you would have received a UCSB NetID when you started using the NanoFab:

https://it.ucsb.edu/ivanti-secure-access-campus-vpn/get-connected-campus-vpn

-- Vraj // Demis D. John 20:08, 22 April 2025 (UTC)

New Gowns: Toolbelts purchases

We are required to switch to new gowns in January. The new gowns won’t have pockets, but you are allowed to purchase cleanroom tool belts. Please ask staff for which tool belts you can purchase.

Two vendors for cleanroom belts we are using are listed here, you may request others:

// Demis D. John 03:34, 3 January 2025 (UTC)

Suss SB6-8E

We found a blown resistor (and a questionable op amp) on one of the boards that contains the z-axis motor circuit. However, we still cannot get the tool to initialize. Next we will try swapping out the hard drive again and run some more tests.

I will send out an update once we have one. -Aidan // Demis D. John 00:35, 8 December 2024 (UTC)

ICP1 Down

The board we were waiting on arrived, but it did not resolve the tool issue. We are working with Panasonic on the next steps. //Vraj Mehalana 14:17, 1 March 2024 (PST)